IDEF’11 Update Part 1: Ongoing Naval Projects

F-511 TCG Heybeliada

Today is the last day of IDEF’11, 10th International Defence Industry Fair. I was visiting the fair for the least two days. It was very tiring event. But there are very to share.

I visited the first IDEF twenty years ago. And I can tell you that there has been a considerable change in the industry. Twenty years ago all the international house hold names of defence industry would come and show their latest gadgets or products and we would marvel at them. Now they are still here but much more humble and sincere. Twenty years ago BAE Systems would show its Type 26 Global Combat Ship and would try to sell it as is. Now they are looking for cooperation and work share and they are ready to have Turkish Navy configure the this as it wishes. I was able to talk about Type 26 with BAE systems in detail. I will write about it later.

The last fair two years ago had a very distinctive naval flair. This year that was not there. Well the obvious reason for this is that the projects of then are swimming ships of today. F-511 TCG Heybeliada, the first ship of Milgem class, P-1200 TCG Tuzla the first ship of the New Type Patrol Boat class were available for external sighting. All these ships were on project phase during the last fair.

This fair’s main attractions were tanks, armoured fighting vehicles, UAV’s and helicopters. But never the less there were a lot of important developments regarding the ongoing naval projects.

Milgem: The first ship TCG Heybeliada will be commissioned in Turkish Navy in July. At the same day the second ship, F-512 TCG Büyükada will be launched.

The model of Moship

Moship/Ratship: The design phase for the submarine rescue ship Moship and two rescue and towing ships Ratship is continuing. I learned out to my surprise that Istanbul Shipyard, the builder was responsible for the whole ship inclusive the mission equipment. That means it is the shipyard will also provide the ROV, the McCann bells and other necessary equipment. It must be a steep learning curve for them. The contract for the production of these ships not signed yet. There was a speculation that it might be signed during the fair but this did not happened.

Model of LST

LST: The contract for the construction of a new LST’s was signed between Ministery of Defence and ADIK_Furtrans shipyard on 11 May 2011. The value of the contract was not disclosed but the ship will be delivered in 48 months. The ships will carry 525 persons, 17 MBT and between 24 – 60 vehicles.

The armament consists of 2 single barrelled 40mm Oto Melara guns, 2 Mk15 Phalanx CIWS, 2 machine guns on a stabilised remote controlled chassis.

The ships will have a Smart Mk2 3D air/surface search radar (which not common for an amphibious ship) 2 AselFLIR 300D EO director, torpedo counter measures systems, laser warning receiver and Link16/22 system. All these sensors and weapons will be controlled by a 5 consoles of GENESIS CMS.

New Type Patrol Boats: The first boat of this class P-1200 TCG Tuzla was launched in 2011 and was handed over to Turkish Navy in 4 January 2011. The second boat P-1201 TCG Karaburun was handed over to Turkish Navy on 19 April 2011 for temporary acceptance. The third and fourth boats, P-1202 TCG Köyceğiz and P-1203 TCG Kumkale are launched as early 2001 and they are currently under going sailing acceptance tests and harbour acceptance test respectively. The fifth boat P-1205 TCG Tarsus will be launched in this month.

In the mean time the construction of the two boats ordered by Turkmenistan in October 2010 is continuing. Dearsan shipyard has shipped the boats in kits, along with the equipment necessary for the construction. According to IDEF’11 Show Daily, the construction of two boats is about to be completed and the installation of the propulsion system will commence soon. These have a very similar weapon and sensor configuration to Turkish boats. The main difference is the Turkmenistan boats will have a Thales Variant 2D air/surface search radar and a pair of 25mm Aselsan STOP systems.

Type 214 Submarines: Interestingly there was very little information available about the current status of this programme. But credit contract for this programme was signed at the end of 2010 thus I assume everything is going as scheduled. Currently STM the main subcontractor of this project is sourcing 18000 components and materials to be used. This is a time consuming process. I do not expect any important development in this project before summer.

6 thoughts on “IDEF’11 Update Part 1: Ongoing Naval Projects

  1. Thank you for the insight into Naval aspects IDEF 2011 (although minimal as the years before as you stated, you’ve included alot of information).

    Will your Part 2, include some details about Koc/RMK LHD. I believe it will be a pivotal point in Turkish Naval Industry, a point where all doubts about Turkish Naval Industry can be squashed.

    1. The techincal details of RMK’s LPD is as follows:
      Lenght oa: 221,3 m
      Beam: 38 m
      Depth: 7,5 m
      Displacement: 28.500 tons fully loaded
      Speed: 22 knots

      The ships will be similar to Navantia’s Juan Carlos I in performance.